The construction site inspection checklist for a routine walk
A routine site walk is the cheapest quality control a project gets. It catches work going wrong while the trade is still on site and the fix costs an hour, not a week. This is the checklist for that walk, and how to record what you find so it gets actioned.
10 minute read. Last reviewed .
What a routine walk is for
A routine walk has four jobs. Check the quality of work in progress against the drawings and the spec. Confirm progress against the programme, area by area, so the next trade is not held up by the last one. Look at housekeeping, because a tidy site is a site where people can see what they are doing. And catch rework early, before it is buried under the next layer of work.
That last one is the money. A pipe run in the wrong place is a ten minute conversation on Tuesday. On Friday, after the plasterboard is up, it is a cut out, a patch, a re-skim and a paint, plus the argument about who pays. Every item you catch on a walk is a rework item that did not happen.
The walk is usually done by the site supervisor or foreman, with the project manager walking less often but more formally. On a small residential job, once a day at the start of the shift is realistic. On a larger project, a daily walk of the active areas and a full walk of the whole site once a week is more common. What matters is that it is routine. A walk that happens when there is time does not happen.
This is a quality and progress checklist. It is not a health and safety audit and it does not replace one. There is a short section below on obvious hazards you should still record, but the site’s own safety inspection regime is a separate thing with its own people and its own paperwork.
Before you walk
Take the current drawings, or the phone with the current set on it. Half the items you find on a walk are the work not matching the drawing, and you cannot check that from memory. Make sure it is the current revision. Walking with a superseded plan produces items that are wrong and costs you credibility with the trades.
Take the previous report. The first thing you do in each area is look at the open items from last time. Are they closed, are they in hand, or has nobody touched them? An item that stays open across three walks is a conversation, not another line on the list.
Take a tape, a level, a torch, and something to record on. Paper works for a walk but it means an hour at the laptop afterwards. A phone with Site Audit on it means the walk and the report are the same job.
Walk early in the shift if you can. Work is exposed, the trades are setting up rather than heads down, and an item you raise at eight o’clock can be fixed by ten. A walk at four in the afternoon finds the same problems after they have been boarded over, and the people who can fix them have gone home.
Walk a fixed route every time. Site entrance and set-up first, then externals and groundworks, then up through the building floor by floor, then back out to materials storage and the compound. A fixed route means you do not skip the area that was fine last week, which is exactly the area where nobody is looking.
The checklist
Not every group applies on every walk. Groundworks are done by the time you are on internal finishes. Run the groups that are live on your site and glance at the rest for damage and protection.
Site set-up and housekeeping
- Site entrance, signage and boundary fencing intact and closed
- Access routes clear of materials, offcuts and stacked waste
- Skips and waste segregation in use, not overflowing
- Welfare, drying area and site office usable and clean
- Temporary power and lighting working in every active area
- Drawings register on site is current and superseded sheets removed
- Deliveries scheduled and a clear laydown area for each
- Site diary and daily records up to date
Groundworks and drainage
- Excavation depths and formation checked against the drawing
- Foundations set out to the correct line and level
- Reinforcement placed with correct cover and tied off before pour
- Drainage runs to the correct falls and line, with joints made
- Pipe bedding and surround in place before backfill
- Inspection chambers and gullies at the right invert levels
- Service ducts and entries in before the slab is poured
- Excavations protected from water and collapse
Structure and frame
- Wall setting out and openings match the current drawing
- Masonry plumb and level, cavities clear of mortar droppings
- Wall ties, lintels and bearings installed as specified
- Steelwork bolted and grouted, with connections complete
- Timber frame plates, studs and noggins at the specified centres
- Floor joists and trusses correctly spaced, strapped and braced
- Temporary propping in place and not removed early
- Damp proof courses and cavity trays lapped and dressed correctly
External envelope
- Roof coverings laid to the correct lap, with ridge and hips fixed
- Flashings, soakers and abutments dressed and sealed
- Gutters and downpipes fixed, with falls and outlets connected
- Windows and external doors installed square and sealed
- Cavity closers, fire stopping and insulation continuous at openings
- Render, cladding or brickwork complete and free of damage
- Membranes and breather layers lapped the right way and taped
- Scaffold ties and holes made good as lifts come down
Internal first fix and services
- Stud partitions set out to the drawing with openings in the right place
- Pipework runs clipped, tested and marked before boarding
- Cable routes safe zones respected, with cables clipped and identified
- Ventilation ducts installed with correct route and supports
- Fire stopping complete at every penetration through a rated wall
- Insulation fitted tight with no gaps, and vapour control layer sealed
- Boxes, backplates and noggins fitted for every fixture on the drawing
- First fix signed off before plasterboard goes up
Internal finishes
- Plasterboard fixed with joints staggered and screws at the right centres
- Plaster and skim flat, corners true, no cracks or hollow patches
- Screeds level, cured and free of cracking before floor finishes
- Tiling level, lines straight, grout complete, movement joints in
- Doors hung with even margins and hardware working
- Skirtings and architraves scribed and fixed tight
- Painting complete with even coverage and clean cut lines
- Second fix electrical and plumbing complete and tested
Externals and landscaping
- Finished ground levels set below damp proof course
- Paths, drives and paving laid to falls away from the building
- Kerbs and edgings true and bedded
- Fencing, gates and retaining walls plumb and secure
- Topsoil, turf and planting to the landscape drawing
- External lighting, taps and meter boxes fitted and working
- Surface water drainage connected, no ponding after rain
- Site cleared of building debris and spoil heaps
Materials storage and protection
- Materials stored off the ground and covered where required
- Plasterboard, timber and insulation kept dry
- Cement and bagged products in date and stacked properly
- Windows, doors and joinery protected from damage after installation
- Finished floors covered before follow-on trades start
- Fragile items such as sanitaryware stored away from traffic
- Stock levels checked against next week's programme
- Damaged or rejected materials quarantined and recorded
Safety items you still note
You are walking for quality and progress, but you will still see things. An unguarded edge, an open excavation with no barrier, a ladder tied to nothing, a cable across an access route, a scaffold with a missing board. Record them as you would any other item, with a photo and a location, and hand them to the person responsible for safety on site straight away rather than leaving them for the report.
That is the limit of it. This walk does not replace the site’s safety inspection regime, the permits, the inductions or the formal audits. If your quality walk is the only time anyone looks at safety on the site, that is a problem the checklist cannot fix.
Recording an item so it gets actioned
An item on a site report is a work instruction to a trade who was not there when you found it. Write it so they can find it, understand it and fix it without ringing you.
- Location: precise enough to stand alone. Plot 4, first floor, bedroom 2, wall to the landing. Not “upstairs bedroom”.
- Description: what you observed, in plain words. “Socket box set 40mm lower than the adjacent one.” Not “sockets wrong”. Record the measurement if there is one.
- Remedy: what you expect to see when it is closed. “Reposition box to match adjacent height before boarding.”
- Trade: who owns it. This is what makes a per-trade list possible later.
- Priority: high, medium or low. High is anything that blocks the next trade or gets buried by it. Low is cosmetic.
- Two photos: a wide shot showing where it is and a close shot showing what it is. One without the other is half an item.
Use the same categories every time. Element first, then trade if it helps, with location and priority kept in their own fields rather than crammed into the title. That way the register can be filtered by trade, by area or by priority in six months when the same defect reappears. There is a working model in the guide to construction defect categories, and more on the wording of an item in how to write a defect report.
Turning the walk into the site report
The report goes out the same day, or it does not go out. A report from Monday’s walk that lands on Thursday describes a site that no longer exists. The trade has moved on, the item is boarded over, and you are now arguing about something nobody can see.
A usable site report has three parts. A summary table at the front with every item, its location, trade, priority and status, so the project manager can read the whole walk in a minute. One page per item with the photos, the description and the remedy, so the trade has everything they need. And a per-trade list, so each subcontractor gets only their items and cannot claim they missed theirs among somebody else’s.
Send it to named people. The full report goes to the project manager and the site file. Each trade gets their own list and nothing else. Ask for a date against each item rather than a general acknowledgement, because “we will get to it” is not a commitment you can check on the next walk.
Building that by hand from phone photos and a notebook takes longer than the walk did. Site Audit does it on the phone as you go. Each item takes as many captioned photos as it needs, with markup on the photo if you want to circle the problem, dictation instead of typing, and fields for trade, priority, status and due date. It works offline, which matters on a site with no signal, and there is no account to set up. When you get to the car you generate the PDF and send it.
It is free for one project, including the finished PDF with a small footer credit line. Pro is a one-off A$29.99, with local pricing varying, and gives you unlimited projects, one filtered report per contractor, CSV export for the register, and no credit line. You can see the output in the sample report.
Tracking open items on the next walk
The next walk starts with the last report. Stand in each area, open the list of items for that area, and check each one. Closed means you looked at it and it is done to the remedy you wrote, not that the trade said it was done. In hand means work has started. Open means nothing has changed.
Keep the statuses simple and use them the same way every time. Open, in progress, closed, and something for items you have agreed to defer or drop. When an item changes status, record the date. The date an item was raised and the date it was closed are the two facts that settle most arguments later.
Do not delete closed items. Keep them in the register with their photos. When a defect reappears at practical completion, the record that shows it was raised, closed and has come back is worth more than any amount of description. It also gives you the pattern: if the same trade has closed the same item on four plots, the problem is not the plot.
Two things make the walk work better over time. The first is photographs that a stranger can act on, covered in the guide to photographing construction defects. The second is knowing what the end of the job looks like, so you are walking towards it from week one. The practical completion checklist is where the routine walk eventually lands.